Adani Commissions 648 MW Solar Project in Tamil Nadu After Evacuation Delays
September 22, 2016
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
Adani Green Energy has successfully commissioned a 648 MW solar project in Kamuthi, Tamil Nadu. The cost of the project was $679 million (~Rs.45.6 billion) and took eight months to complete, according to Adani. Mercom had previously reported that 360 MW out of the total capacity of 648 MW had been commissioned in March 2016 with the remaining 288 MW delayed due to evacuation issues. This latest announcement confirms the full 648 MW solar project has been connected to the grid.