APTEL Approves 289 Days Time Extension for POWERGRID’s Transmission Project
The Tribunal directed CERC to account for delays caused by force majeure events
August 19, 2024
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Appellate Tribunal for Electricity (APTEL) has ruled that POWERGRID Southern Interconnector Transmission System (PSITSL) entitled to an extension of 289 days for the completion of a transmission project, acknowledging that the delay was due to “force majeure” events.