CERC Allows Project More Time for 38 MW Infirm Solar Power Injection
It noted that the project had already declared CoD for 200 MW of the 250 MW project
September 28, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
Save
The Central Electricity Regulatory Commission (CERC) has allowed a solar power generator an additional 45 days to inject infirm power for the balance 38.1 MW capacity of its 250 MW solar project in Barmer, Rajasthan.