CERC Denies Start Date Extension of Medium-Term Open Access for a Solar Project
The Commission, however, directed the CTU to revise the bills for the capacity not commissioned
September 12, 2022
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
Save
The Central Electricity Regulatory Commission (CERC) recently rejected a solar generator’s plea seeking an extension of the start date of medium-term open access (MTOA).