CERC Denies Transfer of Bank Guarantee for Stage-II Connectivity of Wind Projects
CERC said that the bank guarantee furnished against NTPC’s LoA could not be linked to connectivity applied against SECI’s LoA
July 28, 2021
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Central Electricity Regulatory Commission (CERC), in a recent order, rejected ReNew Power’s petition to adjust the bank guarantee upon grant of stage-II connectivity against the letter of award (LoA) issued by Solar Energy Corporation of India (SECI) for 300 MW of wind projects.