CERC Grants Extension to Solar Projects in Rajasthan for Delay in Road Construction
However, the commission observed that unavailability of material required for the construction is not an event covered under force majeure
December 23, 2019
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Central Electricity Regulatory Commission (CERC) has agreed with a petition that argued that the holdup in road construction by the state government delayed the project commissioning, which was beyond the control of the solar developers.