CERC Rejects PGCIL Plea to Condone Delay in Transmission Project
APTEL had directed CERC to re-examine the matter
June 27, 2024
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Central Electricity Regulatory Commission (CERC) has decided not to condone the delay beyond the revised Scheduled Commercial Operation Date (SCOD) of October 31, 2017, for the Vindhyachal-Jabalpur 400 kV 2nd double circuit transmission line project associated with the 750 MW Rewa Ultra Mega Solar Park in Madhya Pradesh.