CERC Rules Transmission Charges Apply Despite Partial Project Commissioning
The Commission found that transmission assets were operational while generation was delayed
April 30, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Central Electricity Regulatory Commission (CERC) has held that renewable energy generators are liable to pay bilateral transmission charges for the associated transmission system until their projects achieve commercial operation. It rejected their request to quash the invoices issued by the Central Transmission Utility of India (CTUIL).