Commissioning Date Extended for a 300 MW Solar Project on the Grounds of ‘Force Majeure’
The developer would have to pay liquidated damages for 34 days of delay in project commissioning
July 15, 2022
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Maharashtra Electricity Regulatory Commission (MERC) recently extended the commissioning date of ACME Heergarh Powertech’s 300 MW solar project in Rajasthan to April 19, 2022, on the ground of ‘force majeure’ events.