Delayed Solar Projects Liable to Reduced Tariff and Payment of Liquidated Damages
Developers are also liable for tariff reduction for the delay in commissioning the projects
October 7, 2021
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Karnataka Electricity Regulatory Commission (KERC) has directed Hubli Electricity Supply Company (HESCOM) to recover liquidated damages from three solar developers for the delay in commissioning the projects.