Developer can Sell Solar Power in Open Market Post Commissioning Date: CERC
The developer had failed to commission the total capacity by the extended commissioning date
June 6, 2023
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Central Electricity Regulatory Commission (CERC) recently ruled that a solar developer was not obligated to supply the commissioned capacity of 62.5 MW after the extended scheduled commissioning date to the Tata Power Delhi Distribution (TPDDL) in terms of the power purchase agreement (PPA). It was free to decide on the sale of power to third-parties or in the open market.