Developer’s Request for Supplementary PPA for a Delayed Solar Thermal Project Rejected
The Karnataka Commission allowed GESCOM to recover liquidated damages for delay in commissioning of the project
August 10, 2021
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Karnataka Electricity Regulatory Commission (KERC), in a recent order, rejected a solar developer’s request for approval of a supplementary power purchase agreement (SPPA) for a delayed project.