Gujarat Regulator Bars Encashment of ₹60 Million Connectivity Guarantee
Gujarat Energy Transmission Corporation must return the bank guarantee within 30 days
November 9, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
Save
The Gujarat Electricity Regulatory Commission (GERC) has restrained Gujarat Energy Transmission Corporation (GETCO) from invoking or encashing a ₹60 million (~$639,352) bank guarantee furnished for Stage II connectivity at the 220 kV Kalawad substation.