Gujarat Regulator Bars Termination of PPA for Delayed 280 MW Solar Project
The Commission declined to restrain GUVNL from encashing the bank guarantee
October 22, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
Save
The Gujarat Electricity Regulatory Commission (GERC) has restrained Gujarat Urja Vikas Nigam (GUVNL) from terminating its power purchase agreement (PPA) for the uncommissioned capacity of a 280 MW solar project until the final adjudication of the developer’s force majeure claims.