Gujarat Regulator Grants 343-Day Extension for 70 MW Wind-Solar Project
The Commission condoned the delay in setting up the power evacuation infrastructure
June 30, 2025
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Gujarat Electricity Regulatory Commission (GERC) has granted a 343-day extension for a 70 MW wind-solar hybrid project to establish its evacuation infrastructure, including the 66 kV transmission line, associated bays, and metering systems.