Gujarat: Solar Projects Up to 400% of Contract Demand Allowed for Desalination Plants
The Commission, however, rejected the relief sought for a banking facility, cross-subsidy surcharge, and additional surcharge
August 4, 2021
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Gujarat Electricity Regulatory Commission (GERC), in a recent order, ruled that seawater desalination programs could set up solar projects with a maximum capacity of 400% of their contract demand with the distribution licensee to meet their energy requirement.