Haryana Commission Denies Long-Term Open Access to a 20 MW Ongoing Solar Project
The Commission rejected the appeal due to the developer’s non-compliance to the state’s solar policy and guidelines
October 14, 2020
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Haryana Electricity Regulatory Commission (HERC) has ruled that the losses suffered by a solar open access project developer due to a delay in the signing of a connectivity agreement was not the fault of Haryana Vidyut Prasaran Nigam (HVPN) and that the developer was not eligible for any compensation for it.