Jaipur-based solar module manufacturer Insolation Energy is planning an ingot and wafer plant in 2027, as it advances the construction of a 4.5 GW solar cell manufacturing line in Narmadapuram, Madhya Pradesh.
The company said investments in the ingot-wafer plant will be approximately ₹1.5 billion (~$16.07 million)/GW, bringing the total to between ₹7 billion (~$74.98 million) and ₹9 billion (~$96.41 million).
“There is overcapacity for solar panels right now, but I don’t think there is for cells, and for ingots and wafers, it is too early to say. Nobody has started installing or commissioning ingots and wafers yet. Everyone has started placing orders for machinery because, as per the Approved List of Models and Manufacturers (ALMM) List III, it should be functional from June 1, 2028. So, there is no benefit in installing it before that. The whole picture for ingots and wafers will start to become clear in 2027,” said Manish Gupta, Chairman and whole-time Director at Insolation Energy.
Increased demand across government-led programs, utility-scale projects, EPC, commercial and industrial distributed solar, and the B2C residential rooftop segment helped the company post a revenue of ₹8.37 billion (~$88.69 million) in the second quarter (Q2) of the financial year (FY) 2027, up 96.5% year-over-year (YoY).
The company posted a profit of ₹250.6 million (~$2.66 million), down 32.2% YoY from ₹369.5 million (~$3.92 million).
The company has a total order book of approximately 2.2 GW. Orders worth 1.3 GW are scheduled for delivery by March 2027, with production slots already allocated.
1H FY 2027
For 1H FY 2027, revenue increased 100.6% YoY to ₹15.82 billion (~$167.70 million) from ₹7.89 billion (~$83.62 million).
The company reported a profit after tax of ₹630.8 million (~$6.69 million), down 21.2% YoY from ₹800.7 million (~$8.49 million).
The company successfully executed ~70 MW of solar projects during the period.
Business Highlights
Insolation Energy operates three solar module manufacturing facilities in Jaipur, Rajasthan, with a combined annual production capacity of 5.5 GW.
The company is also developing an aluminum frame manufacturing facility in Narmadapuram, Madhya Pradesh, with an annual capacity of 18,000 metric tons.
The company said aluminum frames are in strong demand, so it can initially start with 65% of production for captive consumption and sell the remaining 35% on the market. But in the longer term, the entire capacity has been planned with a 1:1:1 sustainability ratio.
The company expects to commission and ramp up its captive TOPCon cell facility and aluminum frame plant as part of its backward integration initiatives to improve operational efficiency, cost competitiveness, and support margin improvement.
Recently, Insolation Energy, through its subsidiary Insolation Green Energy, entered into a five-year strategic partnership with U.S.-based perovskite solar technology company Caelux Corporation to commercialize 3 GW of advanced solar modules. The proposed technology combines Caelux energy-producing glass with India’s N-type TOPCon technology, targeting module efficiency of up to 29% by the end of 2029.
On November 4, 2026, the company reached an important operational milestone, recording its highest-ever single-day dispatch of approximately 16 MW of solar modules.
In July this year, Insolation Green Energy won a ₹5.58 billion (~$58.46 million) contract to supply solar modules to NTPC Renewable Energy.
Outlook
The company targets more than 400 MW of engineering, procurement, and construction (EPC) capacity, as well as operations and maintenance (O&M), by FY 2027.
It also plans to increase its power production capacity to more than 400 MW by FY 2027.
“By December, I feel the market should probably clear up. Whatever international matters are going on, they should also ease to some extent by December, and even international freight has started to ease a little compared to the past. We are certain that 2H FY27 will be better than H1 FY27,” noted Gupta.
The company posted revenue of ₹7.41 billion (~$77.6 million) in Q1, up 104.7% YoY, compared to ₹3.62 billion (~$ 38.41 million).