Karnataka Regulator Reduces Tariff for a Delayed Solar Project of Adani Green
The Regulator also stated that Adani was liable to pay damages due to the delay in project commissioning
July 15, 2020
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Karnataka Electricity Regulatory Commission (KERC) has issued an order denying Adani Green Energy (UP) Limited’s requests for relief under the ‘Force Majeure’ clause of its power purchase agreement (PPA) with the Chamundeswari Electricity Supply Company Limited (CESCL).