Liquidated Damages for Solar Project Delays Attract 18% GST
The authority ruled that commissioning of a project qualifies as ‘supply’ under the GST law
February 22, 2022
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Telangana State Authority for Advance Ruling recently clarified that liquidated damages recovered by a solar developer from an engineering, procurement, and construction (EPC) service provider for the delay in commissioning of a project attract 18% Goods and Services Tax (GST).