Maharashtra DISCOM to Pay ₹7 Million as Delayed Payments to Three Wind Generators
A penalty of 1.25% per month will be charged if the payments are not made in time
November 29, 2019
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Maharashtra Electricity Regulatory Commission (MERC) has directed the Maharashtra State Electricity Distribution Company Limited (MSECDL) to clear its outstanding dues with three wind developers in the state, including interest for delayed payment payment charges (DPC).