Maharashtra To Launch Renewable Energy Deviation Settlement Regulations from Jan 2020
The Maharashtra Electricity Regulatory Commission has granted six months trial period from July 1, 2019, to Jan 1, 2020, to implement Deviation Settlement Mechanism regulations
October 10, 2019
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Maharashtra Electricity Regulatory Commission (MERC) has directed the Maharashtra State Load Despatch Center (MSLDC) to amend its forecasting and scheduling procedure in line with the rules and principles of the commission within two weeks.