Dispute Over One Day Commissioning Delay Causes 30% Solar Tariff Reduction in Karnataka
The solar developer is now entitled to the reduced tariff and is liable for the payment of the liquidated damages.
October 25, 2018
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Karnataka Electricity Regulatory Commission (KERC) has dismissed a petition filed by Emmvee Photovoltaic Power Private Limited, stating that the solar power developer is not entitled to the relief due to project commissioning delay of one day.