Regulator Accords Captive Status to a Wind Project and Asks DISCOM to Refund Charges
The Commission asked BESCOM to refund the cross-subsidy surcharge, additional surcharge, and electricity tax within three months
September 15, 2021
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Karnataka Electricity Regulatory Commission (KERC), in a recent order, ruled that the Green Infra Wind Power Generation owned Harapanahalli Wind Power Plant is a captive power project.