Renewable Projects Under Construction Get 75-Day Extension Amid Covid-19 Crisis
Earlier, MNRE had issued a notification, stating that projects with commissioning date on or after April 1 could claim an extension
June 30, 2021
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
In a move to provide the much-needed relief to renewable developers amid the second surge of Covid-19 pandemic, the Ministry of New and Renewable Energy (MNRE), in its latest notification, has granted an extension of two and half months for projects with commissioning dates between April 1 and June 15, 2021.