Renewable Supply Chain Disruption Due to Coronavirus to Be Treated As Force Majeure
MNRE announced that it will allow time extension in scheduled commissioning of delayed renewable projects
March 23, 2020
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
Considering the adverse impact of the Coronavirus pandemic on the global economy, the Ministry of New and Renewable Energy (MNRE) has issued an official memorandum which states that the time extension in scheduled commissioning of renewable projects due to the disruption of supply chains will be treated as a ‘force majeure’ event.