Solar Power Developer Penalized for Delay in Project Commissioning
The commission ruled that the project will have a tariff of ₹4.36/kWh for the term of the PPA
October 23, 2018
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Karnataka Electricity Regulatory Commission (KERC) has issued an order dismissing the petition filed by Marakka Solar Power Project LL.P stating that it is not entitled to any of the reliefs under force majeure (unforeseeable) events.