Solar Developer’s Plea for Commissioning Deadline Extension Rejected
The developer was asked to pay liquidated damages for the delay in commissioning the projects
September 9, 2022
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Uttar Pradesh Electricity Regulatory Commission (UPERC) recently rejected a solar developer’s plea seeking an extension of the commissioning deadline on the grounds of ‘force majeure’ events and said that the developer was liable to pay liquidated damages for the delay in commissioning the project.