CERC said that the timeline could be extended only through an agreement between the contracted parties
November 2, 2021
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Central Electricity Regulatory Commission (CERC) recently heard a solar developer’s plea for extending the time for commissioning the project considering the delay in the adoption of tariff by the Punjab Electricity Regulatory Commission (PSERC). The Commission said that the extension of time had to be through an agreement between the contracting parties. But at this time, the timeframe for commissioning the project had not lapsed, and there was no reason for intervention.