Tribunal Asks Regulator to Re-Examine Penalty on POWERGRID Due to Project Delay
POWERGRID claimed that the commissioning delay was to ensure capacity was online
March 20, 2023
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Appellate Tribunal for Electricity (APTEL) recently ruled in favor of the Power Grid Corporation of India (POWERGRID) and asked the Central Electricity Regulatory Commission (CERC) to examine the matter regarding the delay in the construction of the transmission system for the evacuation of power from the Rewa Ultra Mega Solar’s (RUMSL) 750 MW solar park afresh.