Uttar Pradesh Commission Rejects Part Commissioning of a 10 MW Open Access Solar Project
The Commission said that the Begumpur project was still to be granted LTOA, and it was premature for the petitioner to seek any relief
July 23, 2021
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Uttar Pradesh Electricity Regulatory Commission (UPERC), in a recent order, ruled that AMPSolar Evolution would not be allowed the part commissioning of its two new projects at Tilhar and Begumpur.