Andhra High Court Asks DISCOMs to Pay Renewable Generators Tariffs Per PPAs Within Six Weeks
The Court observed that 'merit order despatch' does not apply to renewable energy, which runs on a 'must-run' basis
March 16, 2022
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
In a landmark judgment, the High Court of Andhra Pradesh set aside the earlier order passed on September 24, 2019, for paying interim tariff and reaffirmed renewable projects’ ‘must-run’ status.