Daily News Wrap-Up: Thermal Plants Must Install 40% Renewable Power Capacity
FDI in renewables dips 46% in Q3 2023
March 7, 2023
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Ministry of Power has announced that any coal or lignite-based thermal generation station coming up on or after April 1, 2023, must either install or procure renewable energy equivalent to 40% of the thermal generation capacity. Also, any coal or lignite-based thermal generating station with the project’s commercial operation date between April 1, 2023, and March 31, 2025, would be required to comply with the renewable generation obligation of 40% by April 1, 2025.