Government Extends ISTS Charges Waiver for Renewable Projects Hit by Grid Delays
April 22, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
Save
The Ministry of Power has stated that solar and wind projects with a firm start date of connectivity between July 1, 2025, and June 30, 2028, may be considered for an extension of the graded interstate transmission system (ISTS) charge waiver of 75%, 50%, or 25%, as applicable, if commissioning is delayed due to the unavailability of the transmission system.