Gujarat Regulator Grants Partial Relief to 200 MW Wind Power Project
GERC orders recalculation of delay penalties but upholds termination compensation for 38.3 MW of uncommissioned capacity
November 23, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
Save
The Gujarat Electricity Regulatory Commission (GERC) has partially allowed a developer’s plea for an extension of the scheduled commercial operation date (SCOD) for a 200 MW wind power project in Gir Somnath district, Gujarat, due to force majeure events.