SECI Seeks to Encash Bank Guarantee for a Delayed Wind Project, Developer Files Petition
ReNew Wind Energy sought the Commission to direct SECI to not encash its bank guarantee following delays in project implementation due to force majeure events
August 11, 2020
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
ReNew Wind Energy (TN) Private Limited, a subsidiary of ReNew Power, has filed a petition with the Central Electricity Regulatory Commission (CERC) asking it to issue orders restraining the Solar Energy Corporation of India (SECI) from encashing its bank guarantee following delays in project implementation due to force majeure events.